Renewal of the Waldenburg Railway
As part of the project, the track system was converted to meter gauge and the entire infrastructure was renewed, from the substructure to the stops, safety systems, overhead lines and traction power supply. Basler & Hofmann took the lead in the engineering consortium and planned lot 4 between Hölstein and Hirschlang across all planning phases. In addition to the complete renewal of the tracks, a double-track crossing, two new stops, various supporting structures and extensive utility and road construction work had to be planned and implemented on the 2.1-kilometre section. The IG's mandate also included the track alignment and the environmental impact report.
Our services
- Overall management in the engineering consortium
- Project planning, tendering and realization for track and civil engineering, civil engineering, platform facilities and road construction in the Hölstein to Niederdorf section
- Project planning of the track geometry
- Coordination with the railroad engineering equipment.