General drainage plan for the Höfe wastewater association
The joint drainage plan includes all sub-projects in accordance with the GEP model specifications of the Association of Swiss Wastewater and Water Protection Experts. The plant register was completely revised as the basis for the GEP. Basler & Hofmann was invited to tender and provided the services for the revision.
Around 70 special structures were also inspected as part of the development of the (V)GEP. These included stormwater tanks, stormwater overflows and pumping stations. The structures were recorded using laser scanners and 360° cameras. This data was used to create three-dimensional as-built models that can be viewed virtually using a web viewer. This provides spatial information that can be used broadly and efficiently for operations and action planning.
Our services
- Excerpt: Invitation to tender and support for the revision of the asset register
- Recording of around 70 special structures using a laser scanner and 360° camera
- Invitation to tender and evaluation of condition surveys
- Concept and implementation of a measurement campaign for extraneous water
- Development of the data management concept
- Concept for precipitation measurements including planning of a new measuring point
- Assessment of the discharge points into bodies of water
- Development of the drainage concept
- Development of the action plan for the entire perimeter